We continue to make progress on our Vikings Stadium precast project, we set 2,600 pieces to date; 400 pieces still to be placed in the upper bowl and completed by the end of July.  After the upper bowl is finished, we will move to the lower bowl and finish the remaining 2,200 pieces by Christmas.