Aurora Municipal Building

Aurora, CO

Aurora’s City government was quickly outgrowing its outdated facility, and desperately needed to consolidate multiple satellite operations under one roof. Throughout the design process the Aurora City Council and City staff asked for a building that would reflect the rich traditions of the City and give architectural form to the dignity of their government.

This project was a design-build, five-story office building and attached garage for the City of Aurora council offices and municipal departments. Building features also included council chambers, a public broadcasting television studio, a full-service cafeteria and public meeting space, a data center, and outdoor public event space.

Precast Solution

Budget, schedule and Wells Concrete’s total precast approach were key factors in the design team’s selection of structure type for this high profile project.

Key Project Attributes

  • Total Precast
  • Acid Etch
  • 764 Car Parking Structure
  • Cornice Feature
  • (4) Sided Finishes at Colannde

Project and Precast Scope

  • 275,000 SF of Precast Farming
  • 1,575 precast pieces
  • 35 Erection Days with (3) Cranes
  • (5) Story
  • Cast-in Lettering

 


Get in Touch

Dan Parker

Director of Client Services
303.964.7024

Aurora Municipal Building